Median days by permit office

Median days by permit office
Permit officeCountyMedian daysMiddle half (days)Issued permits (n)
Clay County (unincorporated)Clay74–12101
Manatee County (unincorporated) *Manatee118–16935
City of Palm Beach Gardens *Palm Beach138–20195
Okaloosa County (unincorporated) *Okaloosa138–2264
Lake County (unincorporated) *Lake147–27223
City of Bonita SpringsLee147–34155
Marion County (unincorporated) *Marion1712–27232
City of Winter ParkOrange1711–2564
Miami-Dade County (unincorporated)Miami-Dade1910–42536
City of New Smyrna BeachVolusia2214–3282
Hernando County (unincorporated)Hernando2711–49186
Collier County (unincorporated)Collier3329–48660
City of Marco Island *Collier3420–5354
City of Cape CoralLee3520–59628
City of Boca Raton *Palm Beach3618–5988
City of Jupiter *Palm Beach4532–5657
City of OrlandoOrange4834–80124
City of West Palm Beach *Palm Beach5540–78111
City of Delray Beach *Palm Beach6143–9783
City of Miramar *Broward9869–18251
City of Coral GablesMiami-Dade10968–18658

* Partial source: the office's records we could gather may be incomplete. Middle half = 25th to 75th percentile.

How we measured

What this doesn't tell you

Permit time isn't build time. Florida law sets review deadlines once an application is complete (Florida Statutes s. 553.792), and plan corrections add time. See How long it takes to build a pool.

Questions

Why isn't my city in the table?
Its office either doesn't publish both dates, didn't have 50 issued permits in the window, or we couldn't gather its records yet. Ask your permit office for its current review time.
Does a faster office mean a cheaper pool?
No. This measures time only. Use the calculator for a planning estimate.
Is the median a promise?
No. About half of permits took longer. Incomplete applications and plan corrections add time.